Project: Subproject Tasks in Master Project Lose 1 Minute

Q118988


The information in this article applies to:


SYMPTOMS

Subproject tasks in a master project finish one minute early when the subproject files are closed.


CAUSE

The above problem may occur in the master project when the following conditions are true:


STATUS

Microsoft has confirmed this to be a problem in the Microsoft products that are listed at the beginning of this article.


MORE INFORMATION

Steps to Reproduce Behavior in version 4.0

  1. From the File menu, choose New to start a new project.


  2. Enter two tasks, T1 and T2, and enter 1% complete on task T1.


  3. Change the duration on task T2 so that its finish date is either later or earlier than the finish date of task T1.


  4. From the File menu, choose Save. Enter the name SUB.MPP, and choose OK.


  5. From the File menu, choose New to start a new project, and enter a task, T1.


  6. Double-click the task to display the Task Information dialog box. Select the Advanced tab, and enter SUB.MPP as the subproject name. Choose OK.


  7. From the File menu, choose Save. Enter the name MASTER.MPP, and choose OK.

    Note the finish date of task T1 in the master project.


  8. From the File menu, choose Close to close MASTER.MPP. Choose Close again to close SUB.MPP.


  9. From the File menu, choose Open. Select MASTER.MPP and choose OK.


Observe the finish date of task T1. It is now one minute earlier than it was previously.

Additional query words: 3.00a

Keywords :
Issue type : kbbug
Technology : kbHWMAC kbOSMAC kbProjectSearch kbProject400Mac kbProjectMacSearch kbProject300Mac kbProject300 kbProject300a kbProject400


Last Reviewed: November 5, 2000
© 2001 Microsoft Corporation. All rights reserved. Terms of Use.