PRJ: Importing Resources with Units Creates Multiple Resources |
Q119348
When task information is imported or copied into Microsoft Project, duplicate resources may be created.
Resources are duplicated if there is a space between the resource name and the unit, and the resource is assigned to more than one task.
Remove all spaces between the resource name and the unit before importing the task information into Microsoft Project.
| A | B
---------------------------
1 | Task1 | Bob [.3]
2 | Task2 | Bob [.4]
Field Name Align Width Title
---------- ----- ----- -----
ID Right 10
NAME Right 10
RESOURCE NAMES Right 10 Microsoft has confirmed this to be a problem in the Microsoft products listed at the beginning of this article.
Additional query words: 1.10 3.00a duplicated
Keywords : kbinterop kbusage
Issue type : kbbug