PRJ4: Cost Calculated Incorrectly for Resource with Few Hours

Q119349


The information in this article applies to:


SYMPTOMS

In Microsoft Project, when a resource is assigned a small number of work hours and a large amount of cost, the cost of the resource may be calculated incorrectly.


CAUSE

This problem occurs because of the way Microsoft Project rounds numbers.


WORKAROUND

To work around this problem, do either of the following:


STATUS

Microsoft has confirmed this to be a problem in the Microsoft products that are listed at the beginning of this article.


MORE INFORMATION

Steps to Reproduce Behavior

  1. Enter a 1 day duration task.


  2. Assign resource "R1" to the task at 1 Unit.


  3. Change the Standard Rate of the Resource to $100.00/h.


  4. Note the Cost of the task is $800.00 which is correct.


  5. Change the Work of the resource to 1.68h.


NOTE: The Cost of the task is calculated incorrectly to $168.33 (the correct cost is $168.00).

Microsoft Project calculates the cost as follows:

  1. $100.00/h = $1.666666666/m ($100.00/h / 60 minutes)


  2. 1.68h = 101 minutes (1.68h * 60 minutes = 100.8 which rounds up to 101)


  3. $1.666666666/m * 101 minutes = $168.333333333 which rounds to $168.33


Additional query words:

Keywords : kbusage
Issue type : kbbug
Technology : kbHWMAC kbOSMAC kbProjectSearch kbProject400Mac kbProjectMacSearch kbProject400


Last Reviewed: November 5, 2000
© 2001 Microsoft Corporation. All rights reserved. Terms of Use.