PRJ: Gantt Chart Dependency Lines Are Based on Bar Styles
Article ID: 120023
Article Last Modified on 1/19/2007
APPLIES TO
- Microsoft Project 2000 Standard Edition
- Microsoft Project 98 Standard Edition
- Microsoft Project 4.1 Standard Edition
- Microsoft Project 4.0 Standard Edition
- Microsoft Project 4.0 for Macintosh
This article was previously published under Q120023
SUMMARY
In Microsoft Project, the style and color of dependency lines in the Gantt
chart are based on the first bar style that applies to the task that is
listed in the Bar Styles dialog box.
Additional query words: prj2000 relationship
Keywords: kbinfo kbother KB120023