PRJ: Entering Percent Complete Recalculates Project |
Q120383
Your project is recalculated when you enter a value in the Percent Complete box for an unstarted task, even though you set the calculation option to Manual.
When a percent complete is applied to a task, the task's Start date is copied and placed into the Actual Start date. If a schedule recalculation is not performed, the task's start date may be incorrect which would also cause the task's Actual Start date to be incorrect. Therefore, a recalculation is performed when a percent complete is applied to a previously unstarted task so that the Actual Start date will be correct.