PRJ: Calendar Exceptions Calculate Duration Incorrectly

Q120519


The information in this article applies to:


SYMPTOMS

Resource work and Duration values will be calculated incorrectly when an actual start and an actual finish have been entered on a task that has a resource with a calendar exception.


CAUSE

When as task is incomplete and Resource driven, a task's duration is calculated based on the resource that has the greatest amount of work. Once task completes (by marking it 100% complete or entering Actual Start and Finish dates), however, the duration behaves similar to a Fixed duration task and the duration is calculated based on the project calendar instead of the resource's calendar.


WORKAROUND

Because the duration that is calculated by entering the Actual Start and Actual Finish date is incorrect, change the duration to the correct amount based on the resource calendar.


STATUS

Microsoft has confirmed this to be a problem in the Microsoft products that are listed at the beginning of this article.


MORE INFORMATION

Steps to Reproduce Behavior

  1. In the Gantt Chart, enter a task T1 with a duration of 4 days and enter a start date of 8/8/94. The finish date will be 8/11/94.


  2. Assign R1 as a resource.


  3. From the Tools menu, choose Change Working Time.


  4. In the For box, select the calendar for R1.


  5. Select the Day Title for Wednesday, and in the Make Date(s) box choose Nonworking.


  6. Choose OK.


  7. The start and finish dates are now 8/8/94 and 8/12/94.

  8. From the Tools menu, choose Tracking, and then choose Update Tasks.


  9. In the Update Tasks dialog box, enter an actual start date of 8/8/94 and an actual finish date of 8/15/94 and choose OK.


For Project 3.0 and 4.0, note that the task becomes 100 % complete, the start and finish dates are 8/8/94 and 8/15/94, and the duration is changed to 6 days. The Resource Usage view shows that R1 was scheduled for an additional 8 hours on Tuesday of the following week which is 8/16/94. R1 should have been scheduled to work from 8/8/94 to 8/15/94. The resource usage will be incorrect if there are any calendar exceptions between the actual start and actual finish dates.

NOTE: For Project 3.0, the resource usage will be correct if the actual dates are the same as what was originally scheduled in this case 8/8/94 and 8/12/94.

For Project 1.0, you will notice that the task becomes 100 % complete, the start/finish dates are 8/8/94 and 8/15/94, and the duration is still 4 days. The Resource Usage view shows that R1 was scheduled to work from 8/8/94 to 8/12/94 with no work on 8/10/94. The resource should have been scheduled for 8 hours on Monday 8/15/94.

To work around this problem, you would change the duration from 6 days to 5 days.

Additional query words: 3.00a

Keywords : kbusage
Issue type : kbbug
Technology : kbHWMAC kbOSMAC kbProjectSearch kbProject400Mac kbProjectMacSearch kbProject300Mac kbProject110Mac kbProject300 kbProject300a kbProject400 kbProject100


Last Reviewed: November 5, 2000
© 2001 Microsoft Corporation. All rights reserved. Terms of Use.