PRJ4: Actual Start is Reset to NA
Article ID: 120705
Article Last Modified on 11/13/2003
APPLIES TO
- Microsoft Project 4.0 Standard Edition
- Microsoft Project 4.1 Standard Edition
- Microsoft Project 4.0 for Macintosh
This article was previously published under Q120705
SYMPTOMS
In Microsoft Project, the task actual start date will be reset to NA when you change the duration on a task that has the following characteristics
- it has an actual start date
- it is 0-percent complete
- it has a new resource assigned to it
CAUSE
In Microsoft Project the actual start of a task is calculated as NA if the % complete is 0 and a new resource is applied to the task.
NOTE: This behavior is different from Microsoft Project 3.0. In Microsoft Project 3.0, when the % Complete and the % Work Complete fields for a task are set to 0, the Actual Start for that task is not cleared.
STATUS
Microsoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.
Keywords: kbbug kbpending KB120705