PRJ4: Resource Calendar Exceptions Affect Global Exceptions |
Q124536
In Microsoft Project, when you make global changes to a resource calendar, these changes appear as individual calendar exceptions on reports (for example, the changes will appear as individual exceptions on the Resource report).
When you make a resource calendar exception in a given month after making a global exception within the same month, the global exceptions for that month to change to individual exceptions.
Microsoft has confirmed this to be a problem in the Microsoft products that are listed at the beginning of this article.
Additional query words:
Keywords : kbusage
Issue type : kbbug
Technology : kbHWMAC kbOSMAC kbProjectSearch kbProject400Mac kbProjectMacSearch kbProject400
|
Last Reviewed: November 5, 2000 © 2001 Microsoft Corporation. All rights reserved. Terms of Use. |