PRJ4: Resource Calendar Exceptions Affect Global Exceptions

Q124536


The information in this article applies to:


SYMPTOMS

In Microsoft Project, when you make global changes to a resource calendar, these changes appear as individual calendar exceptions on reports (for example, the changes will appear as individual exceptions on the Resource report).


CAUSE

When you make a resource calendar exception in a given month after making a global exception within the same month, the global exceptions for that month to change to individual exceptions.


STATUS

Microsoft has confirmed this to be a problem in the Microsoft products that are listed at the beginning of this article.

Additional query words:

Keywords : kbusage
Issue type : kbbug
Technology : kbHWMAC kbOSMAC kbProjectSearch kbProject400Mac kbProjectMacSearch kbProject400


Last Reviewed: November 5, 2000