In Microsoft Project, when you link the value of a field to the project summary task Name field or Notes field in your project, this linked value is overwritten if you enter a title or comments for your project using the Summary Info dialog box.
NOTE: You do not receive a prompt asking if you want to remove the
link.
Normally, when you enter data in a field that contains a linked value, a dialog box with the following message appears:
However, if the project summary Task Name or Notes field in your project contains a linked value, and you enter a new title or comments for your project using the Summary Info dialog box, the text that you entered in the Title box or the Comments box in the Summary Info dialog box replaces the value in the project summary field without warning. However, the link still exists.Field contains linked data. Okay to remove entire link?
To update the linked value in a project summary Task Name field or Notes field on your project, do the following:
Microsoft has confirmed this to be a problem in the Microsoft products that are listed at the beginning of this article.
You can select the Show Summary Tasks check box on the View tab of the Options dialog box to display summary tasks. With this check box selected, you can select the Project Summary Task check box to display project-level summary tasks. This option is useful when you are viewing consolidated projects.
For more information about the View Tab (Options Dialog Box), choose the Search button in Help and type:
summary tasks: displaying
Additional query words:
Keywords : kbusage
Issue type : kbbug
Technology : kbHWMAC kbOSMAC kbProjectSearch kbProject400Mac kbProjectMacSearch kbProject400
|