Schedule Error in Task with Nonzero Delay Driven by ALAP Task |
Q128620
A task with nonzero delay may be scheduled incorrectly if the following
conditions are true:
To work around this problem, make the ALAP task a predecessor of the problem task with the nonzero delay. If necessary, use negative lag in this workaround relationship so that it does not affect the original logic.
Microsoft has confirmed this to be a problem in the Microsoft products that are listed at the beginning of this article.
Under the above conditions, the delay is correctly ignored when the late finish is calculated for the task with the nonzero delay; however, delay is incorrectly included when the task's finish is calculated. This inclusion of delay creates an amount of negative slack equal to the working time between the late finish and finish dates.
Additional query words: 3.00a
Keywords : kbusage
Issue type : kbbug
Technology : kbHWMAC kbOSMAC kbProjectSearch kbProject400Mac kbProjectMacSearch kbProject300Mac kbProject300 kbProject300a kbProject400
|