PRJ4: Actual Start Dates Deleted When Opening MPX file |
Q132870
When you open a previously saved MPX file in Microsoft Project, the Actual Start Dates for some tasks are changed to NA.
When you open an MPX file, Microsoft Project will remove Actual Start
dates from any MPX file that meets all of the following criteria:
-and-
-and-
To maintain the actual dates for the tasks, use the following steps:
Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.
Additional query words: lost missing N/A
Keywords :
Issue type : kbbug
Technology : kbHWMAC kbOSMAC kbProjectSearch kbProject400Mac kbProjectMacSearch kbProject400
|
Last Reviewed: November 5, 2000 © 2001 Microsoft Corporation. All rights reserved. Terms of Use. |