PRJ4: Start Set to Predecessor's Finish on Task with Resource

Q134663


The information in this article applies to:


SYMPTOMS

When a successor task with resources assigned to it has its percent complete calculated by using Microsoft Project's Update Project feature and the resulting percent complete is less than 100 percent, the start date for the successor task is recalculated to the exact finish date of the predecessor task.


WORKAROUND

To work around this problem, use any of the following methods.


STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.


REFERENCES

For more information about tracking task progress, see the "User's Guide," version 4.0, "Tracking the Progress of Your Project," Chapter 10, pages 149-155.

Additional query words: inaccurate early

Keywords :
Issue type : kbbug
Technology : kbHWMAC kbOSMAC kbProjectSearch kbProject400Mac kbProjectMacSearch kbProject400


Last Reviewed: November 5, 2000
© 2001 Microsoft Corporation. All rights reserved. Terms of Use.