PRJ4: Start Set to Predecessor's Finish on Task with Resource |
Q134663
When a successor task with resources assigned to it has its percent complete calculated by using Microsoft Project's Update Project feature and the resulting percent complete is less than 100 percent, the start date for the successor task is recalculated to the exact finish date of the predecessor task.
To work around this problem, use any of the following methods.
Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.
For more information about tracking task progress, see the "User's Guide," version 4.0, "Tracking the Progress of Your Project," Chapter 10, pages 149-155.
Additional query words: inaccurate early
Keywords :
Issue type : kbbug
Technology : kbHWMAC kbOSMAC kbProjectSearch kbProject400Mac kbProjectMacSearch kbProject400
|