PRJ4: Duration of Linked Task Is Incorrect

Q135012

kbole
The information in this article applies to:


SYMPTOMS

In Microsoft Project, when you paste link information from one project to another, the duration may appear to be incorrect in the destination file.


CAUSE

This behavior occurs if the projects have different default duration units and duration fields have been paste linked.


WORKAROUND

To cause the receiving file to calculate the same duration as the source file, change the Show Duration In parameter to match that of the source file.


MORE INFORMATION

Microsoft Project uses the binary interchange file format (BIFF) to pass information when it creates or uses DDE or OLE links; the data contains only the duration number, not the unit identifier. The unit identifier, then, is chosen from the receiving file's Schedule Options.

Additional query words: transfer receiving paste-link

Keywords :
Issue type : kbprb
Technology : kbHWMAC kbOSMAC kbProjectSearch kbProject400Mac kbProjectMacSearch kbProject400


Last Reviewed: November 5, 2000
© 2001 Microsoft Corporation. All rights reserved. Terms of Use.