PRJ4: Cost Greater Than $21,474,836.47 Displayed as Negative
Article ID: 135990
Article Last Modified on 9/26/2003
APPLIES TO
- Microsoft Project 4.0 Standard Edition
This article was previously published under Q135990
SYMPTOMS
When you use Microsoft Project for the Power Macintosh, cost numbers in
Fixed Cost, Cost, Baseline Cost in the task view columns, and Per/Use Cost
and Cost fields in the resource view columns appear as negative numbers.
CAUSE
This problem occurs when the value in a cost field is greater than
$21,474,836.47 but less than $42,949,672.96.
RESOLUTION
The Cost Calculation Patch for the Power Macintosh is now available from
Microsoft Technical Support. This Patch includes the Microsoft Project 4.0
cost calculation update for the Power Macintosh. This update corrects a
problem you may experience when certain numbers are entered in cost fields.
For more information and instructions on how to obtain this patch, please
see the following article in the Microsoft Knowledge Base:
139783 PRJ4: Cost Calculation Patch for the Power Macintosh