Some Default Calendar Options Are Lost When You Quit Project

Q136760

kbusage
The information in this article applies to:


SYMPTOMS

Calendar options like "Hours Per Day" and "Hours Per Week" are being lost and being reset to the default values.


CAUSE

If the International Country setting is set to a country that does not use a decimal number format, then Microsoft Project sets these options to the default settings when starting.


STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

Additional query words:

Keywords :
Issue type : kbbug
Technology :


Last Reviewed: November 3, 2000