PRJ: Deleting Base Calendar Causes General Protection (GP) Fault
Article ID: 137548
Article Last Modified on 1/19/2007
APPLIES TO
- Microsoft Project 98 Standard Edition
- Microsoft Project 4.0 Standard Edition
This article was previously published under Q137548
SYMPTOMS
After you delete a custom base calendar, you may receive the following
error message:
WINPROJ4 caused a General Protection Fault in module WINPROJ.EXE at 0003:02A1
CAUSE
This problem occurs under the following conditions:
- The base calendar is deleted through the Organizer
- The Resource Graph is the active view
- The resource that is viewed in the graph uses the base calendar that
was deleted
NOTE: If the Resource Graph is formatted to display peak units, the GP fault does not occur.
WORKAROUND
To work around this problem, before you delete the base calendar, either
apply a different view or format the Resource Graph to display peak units.
MORE INFORMATION
Additional query words: gpf gp fault
Keywords: kbbug kbfix KB137548