PRJ: Resource Names Not Updated in Workgroup Message
Article ID: 137842
Article Last Modified on 8/30/2002
APPLIES TO
- Microsoft Project 4.1 Standard Edition
This article was previously published under Q137842
SYMPTOMS
When you use the Workgroup features in Microsoft Project, clicking the
Resource Assignment button does not update the Resource Names field when you add a resource.
NOTE: The Resource Names field is not a default field in the workgroup messages. Resource Names is added manually via the Workgroup customization feature
CAUSE
This problem occurs because the Resource Names field in the TeamAssign dialog box is initialized when the dialog box is opened. Note that the Resource Names field is not synchronized with the To field (which is updated).
WORKAROUND
Click the Send button when the message is ready to be distributed. Clicking Send forces an update of the Resource Name field and distributes the message properly.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
Keywords: kbbug kbinterop kbpending KB137842