Project: MPX File Does Not Preserve Milestone Property
Article ID: 139537
Article Last Modified on 11/25/2003
APPLIES TO
- Microsoft Project 3.0 Standard Edition
- Microsoft Project 4.0 Standard Edition
- Microsoft Project 4.1 Standard Edition
- Microsoft Project 3.0 for Macintosh
- Microsoft Project 4.0 for Macintosh
This article was previously published under Q139537
SYMPTOMS
If you mark a summary task as a milestone, save the file as an MPX file,
and then reopen it, the summary task will no longer be marked as a
milestone.
WORKAROUND
To work around this problem, you must re-enable the milestone setting
manually. To do this, use the following steps:
- Select the summary task.
- On the Insert menu, click Task Information.
- Click the Advanced tab.
- Select the Mark Task As Milestone check box.
- Click OK.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
Additional query words: import export
Keywords: kbbug kbpending kbusage KB139537