Article ID: 141733
Article Last Modified on 1/19/2007
APPLIES TO
- Microsoft Project 2000 Standard Edition
- Microsoft Project 98 Standard Edition
- Microsoft Project 4.1 Standard Edition
- Microsoft Project 4.1a
- Microsoft Project 3.0 Standard Edition
- Microsoft Project 3.0a
- Microsoft Project 4.0 Standard Edition
- Microsoft Project 3.0 for Macintosh
- Microsoft Project 4.0 for Macintosh
This article was previously published under Q141733
SUMMARY
A "hammock" task is dependent on external dates for
both its start and finish dates and, ultimately, its duration. The name, hammock task, is
derived from the way a hammock's shape is determined by the distance
between the points to which it is attached.
As scheduled dates in other tasks change, the duration and start and/or
finish dates of the hammock task change as well. In other words, given
three tasks A, B, and C, task B must start on some date from task A (date
A) and task B must finish on some date from task C (date C). For an
illustration of this task B, see Example 1.
Example 1--Hammock Task B
A
| C
|-----B-----|
The span of time between dates A and C dictate the available time to
accomplish task B. As Date A changes, the start date for task B changes as
well; If date C moves, task B must finish appropriately. The difference
between dates A and C is the duration for task B. See example 2.
Example 2--Date A Late, Date C Early
A
| C
|--B--|
Additional query words: prj2000 how-to hammocking hammocked 3.00a multiple contraints
Keywords: kbhowto kbusage KB141733