SUMMARY
In Microsoft Project, when you share resources from a common resource pool,
you may end up with duplicate resources in your resource list.
MORE INFORMATION
In Microsoft Project, a resource can be assigned to no more than 1000 tasks
(500 for version 1.0 and 1.1). This limit applies across project files when
you share resources from a common resource pool. When a resource is shared,
a duplicate resource name will appear in the Resource sheet if the number
of tasks that the resource is assigned to exceeds 1000 tasks across the
files sharing the resource pool.