PRJ: Duration Not Calculated Correctly from MPX File
Article ID: 145855
Article Last Modified on 1/19/2007
APPLIES TO
- Microsoft Project 2000 Standard Edition
- Microsoft Project 4.0 Standard Edition
- Microsoft Project 4.1 Standard Edition
- Microsoft Project 4.0 for Macintosh
- Microsoft Project 98 Standard Edition
This article was previously published under Q145855
SYMPTOMS
In Microsoft Project, if an MPX file does not contain either Duration,
Start, or Finish in the Task table, the duration of each non-summary task
is set to 1d. However, the Start and Finish dates are calculated correctly
based upon the Resource Assignment work hours for each task.
WORKAROUND
To work around this problem so that you have a correct Duration value, do
one of the following:
- Make sure your MPX file contains a duration, start and finish for
tasks.
-or-
- Reenter the resource's work hours. By doing so, you force Microsoft
Project to recalculate a correct duration value.
-or-
- Enter a correct duration for the task.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
Additional query words: prj2000 import change
Keywords: kbbug kbpending KB145855