TMGR: Linked Condition Refers to Predecessor Tasks
Article ID: 149808
Article Last Modified on 8/17/2005
APPLIES TO
- Microsoft Team Manager 1.0 Standard Edition
This article was previously published under Q149808
SUMMARY
The bar style condition called Linked refers to predecessor tasks that
have dependents or that are driving other tasks, and not to dependent or
successor tasks.
MORE INFORMATION
You can create graph bars that show, based on certain criteria, such as
Linked, Marked, Milestone, Over Budget, Recurring, and so on. The Linked
criteria shows a bar on the predecessor tasks, but not on the successor
tasks.
Additional query words: 1.00
Keywords: KB149808