TMGR: Best Fit Scheduling Not Refreshed Until Dialog Reopens
Article ID: 149820
Article Last Modified on 8/17/2005
APPLIES TO
- Microsoft Team Manager 1.0 Standard Edition
This article was previously published under Q149820
SUMMARY
A task's "Best Fit Scheduling" information is contained on the General tab
in the Task Properties dialog box. This information is not updated or
refreshed until the Task Properties dialog box is closed and reopened.
MORE INFORMATION
When you open the Task Properties dialog box, the "Best Fit Scheduling"
information shows the current schedule information about the task. If you
change fields on the General tab (except name) or on the Schedule tab, the
"Best Fit Scheduling" information displays question marks for all of the
values until the Task Properties dialog box is closed and reopened.
Additional query words: 1.00
Keywords: KB149820