A task's "Best Fit Scheduling" information is contained on the General tab in the Task Properties dialog box. This information is not updated or refreshed until the Task Properties dialog box is closed and reopened.

MORE INFORMATION

When you open the Task Properties dialog box, the "Best Fit Scheduling" information shows the current schedule information about the task. If you change fields on the General tab (except name) or on the Schedule tab, the "Best Fit Scheduling" information displays question marks for all of the values until the Task Properties dialog box is closed and reopened.