PRJ4: AdjustDates macro Seems to Schedule Tasks Incorrectly
Article ID: 149950
Article Last Modified on 11/25/2003
APPLIES TO
- Microsoft Project 4.0 Standard Edition
- Microsoft Project 4.1 Standard Edition
- Microsoft Project 4.1a
- Microsoft Project 4.0 for Macintosh
This article was previously published under Q149950
SUMMARY
The AdjustDates macro supplied with the versions of Microsoft Project
listed above may seem to schedule tasks incorrectly. This behavior occurs
when the scheduled start date of the project file is not the same as the
earliest scheduled start date of the tasks in the project schedule.
When you use the AdjustDates macro, the dates of the tasks may be pushed
out later than the date that was entered during the macro execution.