TMGR: Outline Level of Inserted Tasks Same as the Task Above
Article ID: 150012
Article Last Modified on 8/17/2005
APPLIES TO
- Microsoft Team Manager 1.0 Standard Edition
This article was previously published under Q150012
SYMPTOMS
When you insert or paste tasks, the new tasks are inserted at the same
outline level as the task above it. If you paste the task at the end of a
summary task these new tasks become part of the summary.
WORKAROUND
If the tasks are not pasted or inserted at the desired outline level, do
the following:
- Select the Task tab.
- Select the task or tasks you pasted or inserted.
- On the View menu, click Outlining, and then click Outdent or Indent on
the submenu.
- Repeat Step 3 until you have the outline level you want.