TMGR: Task Percent Complete Is Rounded
Article ID: 150111
Article Last Modified on 8/17/2005
APPLIES TO
- Microsoft Team Manager 1.0 Standard Edition
This article was previously published under Q150111
SUMMARY
In Microsoft Team Manager, progressing tasks that have small values of work
completed, relative to their total work, show a percent complete of 1%.
When the Percent Complete field is displayed, any value less than 1%, but
greater than 0%, is displayed as 1%. This does not have an effect on
Microsoft Team Manager's internal calculations of related functions, like
BCWP (Budgeted Cost of Work Performed).
NOTE: When using OLE Automation into Microsoft Team Manager, the task's
Percent Complete property returns the rounded value.
Additional query words: 1.00
Keywords: KB150111