+                             Project Summary          Project Name:	Fast-IO   4     What type of Project was this: New Functionality  (     Following Life of a Project (Y/N): Y  $     Defect Containment Plan (Y/N): N       Project Start Date:   >     What OpenVMS release did this project integrate into: V7.0  H     What was the integration impact: easily integrated new functionality  <     What was the doneness criteria for integration into the #     OpenVMS release and was it met?     H     Briefly describe, in retrospect, what worked effectively about this E     project?  Were there any major events that impacted this project?   J Major unplanned events surrounded IRP and ACB data structure layout, whichI was done later than I would have liked. I had to rewrite my code twice to ? accommodate changes to IRP layout that were done underneath me.        			Project Metrics         1.Scope of the project: * 				     Starting 	                Actual  				     Estimate 			   +    	1. Size				2000 lines .C		2100 lines .C % 					 400 lines .MAR		 550 lines .MAR  	  	2. Effort and Duration    				Duration	Peak		Effort ! 						Staff	  (ex: person-months)  	 Number of People?  	  1.Pre-integration:  	  2.Post-integration:  	 	Example: H 	  If pre-integration included 4 people for 3 months, 1 person 6 months,9 	  then, Duration = 6, Peak Staff = 5, Effort = 18 months   !     2. Release Integration Dates:        3. Number of Defects:   ;     Defect             Project  	First 	   Last 	   Actual  >     Removal 	       Phase		Defect	   Defect          Number of2     Activity				Estimate   Estimate        Defects     1.     2.     3.     4.     5.     6.   ...    Total 