1 SAPC Upgrade Information Introduction
This document contains information needed for upgrading to SAPC 1.3 .
This document is to be used when planning upgrades on customer sites and covers the following topics:
- Upgrade Prerequisites
- Upgrade Impact
This document is intended for personnel handling the planning of the upgrade of the SAPC.
1.1 SAPC Upgrade Information Prerequisites
This section describes the prerequisites which must be fulfilled before the SAPC can be upgraded to.
1.1.1 Hardware Requirements
- External Machine.
- At least 6 GB of free space in mounted hard disk at /cluster.
Following SAPC deployment layouts are supported for upgrade information:
- BSP 8100 (2SCs + 10PLs)
- NSP 6.1 (2SCs + 10PLs)
- VNF deployment (2SCs + 2PLs)
- VNF deployment (2SCs + 10PLs)
1.1.2 Software Requirements
The required SAPC SW components and versions are as follows:
- From: SAPC 1.0 (CXP 903 0138/7 R1B44) onwards, until SAPC 1.2(CXP 903 0138/7 R3A)
- From: SAPC 1.2(CXP 903 0138/7 R3A) onwards
- To: SAPC 1.3 (CXP 903 0138/7 R4A)
1.2 Related Information
The complete information of the upgrade process can be found in the following documents:
2 Upgrade Overview
This section describes the upgrade procedure from an impact point of view.
2.1 Lead Times of Upgrade to SAPC 1.3
For information on the lead time for upgrading the SAPC broken down into steps, see Table 1.
|
SAPC |
Estimated Time (Minutes) |
Estimated Time during Maintenance Window (Hours)(1) |
Comment | ||||||
|---|---|---|---|---|---|---|---|---|---|
|
Pre Phase |
Upgrade |
Post Phase | |||||||
|
Backup |
Pre Steps |
Health Check |
Health Check |
Post Steps |
Backup | ||||
|
Off Maintenance Window |
During Maintenance Window | ||||||||
|
BSP 8100 2+10PLs |
5 |
10 |
5 |
30 |
5 |
5 |
2 |
||
|
NSP 6.1 2+10PLs |
5 |
10 |
5 |
55 |
5 |
5 |
2 |
||
|
2+2PLs(2) |
5 |
10 |
5 |
30 |
5 |
5 |
2 |
||
|
2+10PLs(3) |
5 |
10 |
5 |
30 |
5 |
5 |
2 |
||
(1) Including a hypothetical RollBack procedure.
For information on the lead time for upgrading the SAPC broken down into steps, see Table 2.
|
SAPC |
Estimated Time (Minutes) |
Estimated Time during Maintenance Window (Hours)(1) |
Comment | ||||||
|---|---|---|---|---|---|---|---|---|---|
|
Pre Phase |
Upgrade(2) |
Post Phase | |||||||
|
Backup |
Pre Steps |
Health Check |
Health Check |
Post Steps |
Backup | ||||
|
Off Maintenance Window |
During Maintenance Window | ||||||||
|
BSP 8100 2+10PLs |
5 |
10 |
5 |
85 |
5 |
5 |
3 |
||
|
NSP 6.1 2+10PLs |
5 |
10 |
5 |
140 |
5 |
5 |
4 |
||
|
2+2PLs(3) |
5 |
10 |
5 |
45 |
5 |
5 |
2 |
||
|
2+10PLs(4) |
5 |
10 |
5 |
160 |
5 |
5 |
4 |
||
(1) Including a hypothetical RollBack procedure.
(2) The upgrade time is directly proportional to amount
of Pay Loads.
2.2 Downtime
2.3 Traffic Loss
During the upgrade the following traffic loss is expected:
|
SAPC |
Estimated traffic loss time (Minutes) |
Comment |
|---|---|---|
|
BSP 8100 2+10PLs |
13 |
|
|
NSP 6.1 2+10PLs |
20 |
|
|
2+2PLs(1) |
12 |
|
|
2+10PLs(2) |
12 |
Less than 2% traffic loss.
2.4 Service Disturbances
During the upgrade the following impact on services is expected:
- The Measurements handling by the Performance Manager are stopped during the Upgrade procedure.