1   Introduction

This document provides information about the upgrade of vMTAS from 1.2.1 to 1.4.

This document is to be used when planning upgrades on customer sites.

Scope

This document covers the following topics:

Target Groups

The software upgrade procedure is normally done (or overseen) by Ericsson maintenance personnel.

1.1   Prerequisites

This section describes the prerequisites which must be fulfilled before performing the MTAS upgrade.

1.1.1   Licenses

Make sure that needed licenses are installed before the installation of the MTAS upgrade packages.

1.1.2   Update of Charging System

Update the charging system, if applicable, with the new charging XML files to prepare for the new charging AVPs and enumeration values.

Note:  
Use the described charging system instead of Multi-Mediation (MM) as the MTAS can interact with other types of charging systems.

To perform the charging system update, refer to MTAS Charging Management GuideMTAS Charging Management Guide, Reference [7].

For more details of the XML specifications, refer to the following files:

1.1.3   Hardware and Software Required

This section describes the required hardware and software.

Network Element Version

This instruction applies to the following Network Elements (NEs):

Hardware Configurations

The supported Hardware (HW) configurations are as follows:

From Software Configuration States

To Software Configuration States

1.1.4   Documents

Before starting this procedure, ensure that the following information or documents are available:

1.1.5   Tools

The following tool must be available before performing any procedure in this document:

1.1.6   Conditions

The following conditions must apply:

1.1.7   Prerequisites for Upgrading MTAS with Network Redundancy

  1. The IMS network must be configured for AS failover. That is the AS FQDN has to have at least two DNS entries, one per used MTAS. For information on how to configure MTAS for Dynamic Allocation, refer to sections Configuration for Dynamic Allocation and DNS Based Redundancy and Load Sharing of External Server Nodes in MTAS External Network ConfigurationMTAS External Network Configuration, Reference [8].
  2. Verify that the intended secondary MTAS node(s) is/are operational by following the MTAS Health Check procedure, refer to MTAS Health CheckMTAS Health Check, Reference [9].

1.2   Limitations

The following limitations apply:

1.3   Related Information

The MTAS Trademark information, typographic conventions, definitions, and explanation of acronyms and terminology can be found in the following documents:

Impact of upgrade, rollback, and parameter changes can be found in Virtualized MTAS Network Impact Report from 1.2.1 to 1.4Virtualized MTAS Network Impact Report from 1.2.1 to 1.4, Reference [10].

1.4   Revision Information

This is the first release of this document.

2   Upgrade Overview

This section describes the upgrade, and a possible rollback, from an impact point of view.

Lead Time

For information about lead times (minutes) for the MTAS upgrade, see Table 1.

Table 1    Overall Lead Time for MTAS Upgrade
 

2+2

2+4

2+10

Pre-Upgrade

120 minutes

120 minutes

120 minutes

Upgrade

60 minutes

150 minutes

210 minutes

Post-Upgrade

30 minutes

30 minutes

30 minutes

Down Time

No down time is expected during the upgrade.

Traffic Loss

During the upgrade the following traffic loss is expected:

Service Disturbances

Stable calls stay connected during the upgrade.

2.1   Impact of Upgrade

This section describes the impact of the upgrade.

Operation and Maintenance

The upgrade has the following impact on the operation and maintenance of the system:

Provisioning

Provisioning is not supported during the upgrade.

Charging

No impact.

Security

Security is not treated in this document.

End Terminals

No impact.

Database Handling

No impact.

Dependencies to Other Nodes

This subsection describes the impact on the dependencies to other nodes during the upgrade.

The external interfaces are impacted as follows by the upgrade:

For more information about new, modified, obsolete, or temporary parameters during the upgrade, refer to Virtualized MTAS Network Impact Report from 1.2.1 to 1.4Virtualized MTAS Network Impact Report from 1.2.1 to 1.4, Reference [10].

Other Impacts

No other impacts.

2.2   Impact of Rollback

This section describes the impact of a possible rollback, in case the upgrade is not concluded in a satisfactory manner.

Traffic Loss

See Section Traffic LossSection Traffic Loss on Traffic Loss.

Service Disturbances

See Section Service DisturbancesSection Service Disturbances on Service Disturbances.

Provisioning

See Section ProvisioningSection Provisioning on Provisioning.

Charging

See Section ChargingSection Charging on Charging.

Security

See Section SecuritySection Security on Security.

End Terminals

See Section End TerminalsSection End Terminals on End Terminals.

Database Handling

No Impact.

Rollback Dependencies on Interaction with Other Nodes

See Section Dependencies to Other NodesSection Dependencies to Other Nodes on Dependencies to Other Nodes.

Other Impacts

No impact.

3   Parameter Changes

For more information about parameters which are new, modified, or made obsolete during the upgrade, refer to Virtualized MTAS Network Impact Report from 1.2.1 to 1.4Virtualized MTAS Network Impact Report from 1.2.1 to 1.4, Reference [10].


Reference List

Ericsson Documents
[1] Create Backup, OPERATING INSTRUCTIONS, 3/1543-APA 901 44/1
[2] Glossary of Terms and Acronyms, TERMINOLOGY, 1/0033-AVA 901 29/9
[3] Data Collection Guideline for MTAS, OPERATING INSTRUCTIONS, 70/1543-AVA 901 29/9
[4] Ericsson Command-Line Interface User Guide, USER GUIDE, 1/1553-APA 901 44/1
[5] Managed Object Model (MOM) MANAGED OBJECT MODEL, 155 54-LZN 765 0163/9-V1
[6] MTAS, Communication Details, 3GPP R7 XML, PROCESSING SPEC. 4/190 04-AVA 901 18
[7] MTAS Charging Management Guide, OPERATING INSTRUCTIONS, 3/1553-AVA 901 29/9
[8] MTAS External Network Configuration, USER GUIDE, 43/1553-AVA 901 29/9
[9] MTAS Health Check, OPERATING INSTRUCTIONS, 53/1543-AVA 901 29/9
[10] Virtualized MTAS Network Impact Report from 1.2.1 to 1.4, NETWORK IMPACT REPORT, 18/109 48-AVA 901 29/9-3
[11] MTAS, Offline Charging, 3GPP R7 MM XML, TECHNICAL DOCUMENT, 2/190 04-AVA 901 18
[12] MTAS, Offline Charging, 3GPP R9 MM XML, TECHNICAL DOCUMENT, 5/190 04-AVA 901 18
[13] MTAS, Offline Charging, 3GPP R12 MM XML, TECHNICAL DOCUMENT, 15/190 04-AVA 901 18
[14] MTAS, Online Charging, 3GPP R7 MM XML, TECHNICAL DOCUMENT, 3/190 04-AVA 901 18
[15] MTAS, Online Charging, 3GPP R9 MM XML, TECHNICAL DOCUMENT, 6/190 04-AVA 901 18
[16] MTAS, Online Charging, 3GPP R12 MM XML, TECHNICAL DOCUMENT, 16/190 04-AVA 901 18
[17] Restore Backup, OPERATING INSTRUCTIONS, 13/1543-APA 901 44/1
[18] System Backup and Restore, DESCRIPTION, 5/1551-AVA 901 29/9
[19] Trademark Information, LIST, 2/006 51-AVA 901 29/9
[20] Typographic Conventions, DESCRIPTION, 1/1551-FCK 101 05
Other References
[21] SW Gateway. https://swgateway.ericsson.net/
[22] IMS PLM Homepage. https://ericoll.internal.ericsson.com/sites/MTAS_Portal/plm/default.aspx


Copyright

© Ericsson AB 2016. All rights reserved. No part of this document may be reproduced in any form without the written permission of the copyright owner.

Disclaimer

The contents of this document are subject to revision without notice due to continued progress in methodology, design and manufacturing. Ericsson shall have no liability for any error or damage of any kind resulting from the use of this document.

Trademark List
All trademarks mentioned herein are the property of their respective owners. These are shown in the document Trademark Information.

    vMTAS Upgrade Information from 1.2.1 to 1.4         MTAS