1 Introduction
This document provides information about the upgrade of vMTAS from 1.2.1 to 1.4.
This document is to be used when planning upgrades on customer sites.
Scope
This document covers the following topics:
- Upgrade Prerequisites
- Upgrade Overview
Target Groups
The software upgrade procedure is normally done (or overseen) by Ericsson maintenance personnel.
1.1 Prerequisites
This section describes the prerequisites which must be fulfilled before performing the MTAS upgrade.
1.1.1 Licenses
Make sure that needed licenses are installed before the installation of the MTAS upgrade packages.
1.1.2 Update of Charging System
Update the charging system, if applicable, with the new charging XML files to prepare for the new charging AVPs and enumeration values.
- Note:
- Use the described charging system instead of Multi-Mediation (MM) as the MTAS can interact with other types of charging systems.
To perform the charging system update, refer to MTAS Charging Management GuideMTAS Charging Management Guide, Reference [7].
For more details of the XML specifications, refer to the following files:
- MTAS, Communication Details, 3GPP R7 XMLMTAS, Communication Details, 3GPP R7 XML, Reference [6]
- MTAS, Offline Charging, 3GPP R7 MM XMLMTAS, Offline Charging, 3GPP R7 MM XML, Reference [11]
- MTAS, Offline Charging, 3GPP R9 MM XMLMTAS, Offline Charging, 3GPP R9 MM XML, Reference [12]
- MTAS, Offline Charging, 3GPP R12 MM XMLMTAS, Offline Charging, 3GPP R12 MM XML, Reference [13]
- MTAS, Online Charging, 3GPP R7 MM XMLMTAS, Online Charging, 3GPP R7 MM XML, Reference [14]
- MTAS, Online Charging, 3GPP R9 MM XMLMTAS, Online Charging, 3GPP R9 MM XML, Reference [15]
- MTAS, Online Charging, 3GPP R12 MM XMLMTAS, Online Charging, 3GPP R12 MM XML, Reference [16]
1.1.3 Hardware and Software Required
This section describes the required hardware and software.
Network Element Version
This instruction applies to the following Network Elements (NEs):
- MTASv 1.2.1: CXP9025660/9 R4F01
Hardware Configurations
The supported Hardware (HW) configurations are as follows:
From Software Configuration States
- MTASv 1.2.1: CXP9025660/9 R4F01
Platform Level
To Software Configuration States
- vMTAS 1.4: CXP9025660/9 R5A11
Platform Level
1.1.4 Documents
Before starting this procedure, ensure that the following information or documents are available:
- Information (facts) as, node name, software version, platform, operating system, and hardware.
- For information about IP addresses, usernames and passwords, how to collect data and log files, refer to Data Collection Guideline for MTASData Collection Guideline for MTAS, Reference [3].
- For information about how to make backup and restore
procedures, refer to the following document:
- System Backup and RestoreSystem Backup and Restore , Reference [18]
- Restore BackupRestore Backup , Reference [17]
- Create BackupCreate Backup, Reference [1]
- For information about the Ericsson Command-Line Interface
(ECLI), refer to Ericsson Command-Line Interface User GuideEricsson Command-Line Interface
User Guide, Reference [4].
- For information about the Managed Object Model (MOM),
refer to Managed Object Model (MOM)Managed Object Model (MOM), Reference [5].
- Some of the recovery steps require physical access to the nodes for pressing buttons, replacing hardware, and so on. For information on physical access and handling, refer to MTAS Health CheckMTAS Health Check, Reference [9].
1.1.5 Tools
The following tool must be available before performing any procedure in this document:
1.1.6 Conditions
The following conditions must apply:
- The upgrade is supported with a 30% average CPU load traffic limit on the Pay Load Blades.
- An Ericsson Command-Line Interface (ECLI) session in Exec mode is in progress.
1.1.7 Prerequisites for Upgrading MTAS with Network Redundancy
- The IMS network must be configured for AS failover. That is the AS FQDN has to have at least two DNS entries, one per used MTAS. For information on how to configure MTAS for Dynamic Allocation, refer to sections Configuration for Dynamic Allocation and DNS Based Redundancy and Load Sharing of External Server Nodes in MTAS External Network ConfigurationMTAS External Network Configuration, Reference [8].
- Verify that the intended secondary MTAS node(s) is/are operational by following the MTAS Health Check procedure, refer to MTAS Health CheckMTAS Health Check, Reference [9].
1.2 Limitations
The following limitations apply:
- Provisioning is not allowed during the upgrade as configuration changes during upgrade can cause problems.
- It is not supported to use AppTrace during software upgrade.
- There is a risk of traffic loss and generation of new alarms if the diameter link restarts.
- Subscriber Data query or purge operations are not supported during upgrade.
1.3 Related Information
The MTAS Trademark information, typographic conventions, definitions, and explanation of acronyms and terminology can be found in the following documents:
- Glossary of Terms and AcronymsGlossary of Terms and Acronyms, Reference [2]
- Trademark InformationTrademark Information, Reference [19]
- Typographic ConventionsTypographic Conventions, Reference [20]
Impact of upgrade, rollback, and parameter changes can be found in Virtualized MTAS Network Impact Report from 1.2.1 to 1.4Virtualized MTAS Network Impact Report from 1.2.1 to 1.4, Reference [10].
1.4 Revision Information
This is the first release of this document.
2 Upgrade Overview
This section describes the upgrade, and a possible rollback, from an impact point of view.
Lead Time
For information about lead times (minutes) for the MTAS upgrade, see Table 1.
|
2+2 |
2+4 |
2+10 | |
|---|---|---|---|
|
Pre-Upgrade |
120 minutes |
120 minutes |
120 minutes |
|
Upgrade |
60 minutes |
150 minutes |
210 minutes |
|
Post-Upgrade |
30 minutes |
30 minutes |
30 minutes |
Down Time
No down time is expected during the upgrade.
Traffic Loss
During the upgrade the following traffic loss is expected:
- Rejected traffic: None
Three Party (3PTY) sessions and conferences are lost.
- Disconnected traffic: None
Service Disturbances
Stable calls stay connected during the upgrade.
2.1 Impact of Upgrade
This section describes the impact of the upgrade.
Operation and Maintenance
The upgrade has the following impact on the operation and maintenance of the system:
- Alarms
The following alarms can appear, but are automatically resolved:
There are no alarms. - Notifications or Events
The following notifications appear during or after the upgrade procedure:
- Capsule Abortion
These notifications require no actions.
- Counters
The error counters are expected to increase during the upgrade.
Provisioning
Provisioning is not supported during the upgrade.
Charging
Security
Security is not treated in this document.
End Terminals
Database Handling
Dependencies to Other Nodes
This subsection describes the impact on the dependencies to other nodes during the upgrade.
The external interfaces are impacted as follows by the upgrade:
For more information about new, modified, obsolete, or temporary parameters during the upgrade, refer to Virtualized MTAS Network Impact Report from 1.2.1 to 1.4Virtualized MTAS Network Impact Report from 1.2.1 to 1.4, Reference [10].
Other Impacts
No other impacts.
2.2 Impact of Rollback
This section describes the impact of a possible rollback, in case the upgrade is not concluded in a satisfactory manner.
Traffic Loss
See Section Traffic LossSection Traffic Loss on Traffic Loss.
Service Disturbances
See Section Service DisturbancesSection Service Disturbances on Service Disturbances.
Provisioning
See Section ProvisioningSection Provisioning on Provisioning.
Charging
See Section ChargingSection Charging on Charging.
Security
See Section SecuritySection Security on Security.
End Terminals
See Section End TerminalsSection End Terminals on End Terminals.
Database Handling
No Impact.
Rollback Dependencies on Interaction with Other Nodes
See Section Dependencies to Other NodesSection Dependencies to Other Nodes on Dependencies to Other Nodes.
Other Impacts
No impact.
3 Parameter Changes
For more information about parameters which are new, modified, or made obsolete during the upgrade, refer to Virtualized MTAS Network Impact Report from 1.2.1 to 1.4Virtualized MTAS Network Impact Report from 1.2.1 to 1.4, Reference [10].
Reference List
| Ericsson Documents |
|---|
| [1] Create Backup, OPERATING INSTRUCTIONS, 3/1543-APA 901 44/1 |
| [2] Glossary of Terms and Acronyms, TERMINOLOGY, 1/0033-AVA 901 29/9 |
| [3] Data Collection Guideline for MTAS, OPERATING INSTRUCTIONS, 70/1543-AVA 901 29/9 |
| [4] Ericsson Command-Line Interface User Guide, USER GUIDE, 1/1553-APA 901 44/1 |
| [5] Managed Object Model (MOM) MANAGED OBJECT MODEL, 155 54-LZN 765 0163/9-V1 |
| [6] MTAS, Communication Details, 3GPP R7 XML, PROCESSING SPEC. 4/190 04-AVA 901 18 |
| [7] MTAS Charging Management Guide, OPERATING INSTRUCTIONS, 3/1553-AVA 901 29/9 |
| [8] MTAS External Network Configuration, USER GUIDE, 43/1553-AVA 901 29/9 |
| [9] MTAS Health Check, OPERATING INSTRUCTIONS, 53/1543-AVA 901 29/9 |
| [10] Virtualized MTAS Network Impact Report from 1.2.1 to 1.4, NETWORK IMPACT REPORT, 18/109 48-AVA 901 29/9-3 |
| [11] MTAS, Offline Charging, 3GPP R7 MM XML, TECHNICAL DOCUMENT, 2/190 04-AVA 901 18 |
| [12] MTAS, Offline Charging, 3GPP R9 MM XML, TECHNICAL DOCUMENT, 5/190 04-AVA 901 18 |
| [13] MTAS, Offline Charging, 3GPP R12 MM XML, TECHNICAL DOCUMENT, 15/190 04-AVA 901 18 |
| [14] MTAS, Online Charging, 3GPP R7 MM XML, TECHNICAL DOCUMENT, 3/190 04-AVA 901 18 |
| [15] MTAS, Online Charging, 3GPP R9 MM XML, TECHNICAL DOCUMENT, 6/190 04-AVA 901 18 |
| [16] MTAS, Online Charging, 3GPP R12 MM XML, TECHNICAL DOCUMENT, 16/190 04-AVA 901 18 |
| [17] Restore Backup, OPERATING INSTRUCTIONS, 13/1543-APA 901 44/1 |
| [18] System Backup and Restore, DESCRIPTION, 5/1551-AVA 901 29/9 |
| [19] Trademark Information, LIST, 2/006 51-AVA 901 29/9 |
| [20] Typographic Conventions, DESCRIPTION, 1/1551-FCK 101 05 |
| Other References |
|---|
| [21] SW Gateway. https://swgateway.ericsson.net/ |
| [22] IMS PLM Homepage. https://ericoll.internal.ericsson.com/sites/MTAS_Portal/plm/default.aspx |

Contents