A Fallback Operation will soon be started

Contents

1Introduction
1.1Alarm Description
1.2Prerequisites

2

Procedure
2.1Analyzing Alarm
2.2Actions for Canceling Upgrade Process
2.3Actions for Continuing from State WAITING_FOR_COMMIT
2.4Actions for Continuing from State ACTIVATION_STEP_COMPLETED

1   Introduction

This instruction concerns alarm handling.

1.1   Alarm Description

The alarm is raised when a fallback operation is started soon.

The possible alarm causes and fault locations are explained in Table 1.

Table 1    Alarm Causes

Alarm Cause

Description

Fault Reason

Fault Location

Impact

A fallback operation is started soon

The time configured to give the user an opportunity to verify the proper function of the new software version, before committing or canceling the upgrade, is coming to an end

Attribute state is in state WAITING_FOR_COMMIT.


Timer timeRemainingBeforeFallback counts down below the alarmBeforeTimeout value.

Upgrade package

The ongoing upgrade process is automatically canceled unless the user starts the commit action before timer timeRemainingBeforeFallback reaches 0

The time configured to give the user an opportunity to verify the proper function of a step in the upgrade to a new software version, before continuing with the next step or canceling the upgrade, is coming to an end

Attribute state is in state ACTIVATION_STEP_COMPLETED.


Timer timeRemainingBeforeFallback counts down below the alarmBeforeTimeout value.

The ongoing upgrade process is automatically canceled unless the user starts the activate action before timer timeRemainingBeforeFallback reaches 0

The time configured for upgrade to a new software version, before continuing with the next step or canceling the upgrade, is coming to an end

Attribute state is in state ACTIVATION_IN_PROGRESS. Timer timeRemainingBeforeFallback counts down below the alarmBeforeTimeout value.

The ongoing upgrade process is canceled

The alarm is raised only during a software upgrade process.

The alarm attributes are listed and explained in Table 2.

Table 2    Alarm Attributes

Attribute Name

Attribute Value

Major Type

193

Minor Type

65537

Managed Object Class

SwM

Managed Object Instance

ManagedElement=<node_name>,SystemFunctions=1,SwM=1,Upgradepackage=<upgrade_package>

Specific Problem

A Fallback Operation will soon be started

Event Type

other (1)

Probable Cause

timeoutExpired (164)

Additional Text

A Fallback Operation will soon be started

Perceived Severity

warning (6)

1.2   Prerequisites

This section provides information on the documents, tools, and conditions that apply to the procedure.

1.2.1   Documents

This instruction references the following document:

1.2.2   Tools

No tools are required.

1.2.3   Conditions

Before starting this procedure, ensure that the following conditions are met:

2   Procedure

This section describes the procedure to follow when this alarm is received.

2.1   Analyzing Alarm

Do the following:

  1. Was the alarm raised during initial installation?

    Yes: Contact the deployment organization. Proceed with Step 3.

    No: Continue with the next step.

  2. Select the appropriate action:
  3. Job is completed.

2.2   Actions for Canceling Upgrade Process

Do the following:

  1. Navigate to the UpgradePackage Managed Object (MO), for example:

    >dn ManagedElement=NODE06ST,SystemFunctions=1,SwM=1,Upgradepackage=ERIC_UP-CXP9020355_1-R7F01

  2. Cancel the upgrade process:

    (Upgradepackage=ERIC_UP-CXP9020355_1-R7F01)>cancel

  3. Is the alarm cleared?

    Yes: Proceed with Step 6.

    No: Continue with the next step.

  4. Perform data collection, refer to Data Collection Guideline.
  5. Consult the next level of maintenance support. Further actions are outside the scope of this instruction.
  6. Job is completed.

2.3   Actions for Continuing from State WAITING_FOR_COMMIT

Do the following:

  1. Commit the upgrade process by using action commit in the UpgradePackage MO:

    (Upgradepackage=ERIC_UP-CXP9020355_1-R7F01)>commit

    Note:  
    This action is executed in Exec mode. This is different from ECLI command commit used to apply configuration changes in Config mode.

  2. Is the alarm cleared?

    Yes: Proceed with Step 5.

    No: Continue with the next step.

  3. Perform data collection, refer to Data Collection Guideline.
  4. Consult the next level of maintenance support. Further actions are outside the scope of this instruction.
  5. Job is completed.

2.4   Actions for Continuing from State ACTIVATION_STEP_COMPLETED

Do the following:

  1. Take the upgrade package into operation:

    (Upgradepackage=ERIC_UP-CXP9020355_1-R7F01)>activate

  2. Is the alarm cleared?

    Yes: Proceed with Step 5.

    No: Continue with the next step.

  3. Perform data collection, refer to Data Collection Guideline.
  4. Consult the next level of maintenance support. Further actions are outside the scope of this instruction.
  5. Job is completed.


Copyright

© Ericsson AB 2014, 2015. All rights reserved. No part of this document may be reproduced in any form without the written permission of the copyright owner.

Disclaimer

The contents of this document are subject to revision without notice due to continued progress in methodology, design and manufacturing. Ericsson shall have no liability for any error or damage of any kind resulting from the use of this document.

Trademark List
All trademarks mentioned herein are the property of their respective owners. These are shown in the document Trademark Information.

    A Fallback Operation will soon be started